The Mundra Windtech project involved the design, supply and erection of a pre-engineered building (PEB), with specific grade materials selected due to the corrosive nature of the site. Complete insulation was required as the plant was fully air-conditioned; all fasteners were hot-dip galvanized to ensure long-term durability and corrosion resistance.
The entire scope of 4000MT was successfully completed within 9 months. All hot-rolled members were required to have a minimum strength of 250MPa. A remarkable erection record of 254MT was achieved in a single day. Additionally, a three-coat painting system with a total thickness of 325 microns was applied, considering the project's coastal location.
The success of this project ensured that we receive a repeat order of large volume. At M&B Engineering, we are fully committed to managing large orders efficiently and ensuring project completion to the highest standards.